248 Central Av #0
San Francisco permit 202602186085 · Haight Ashbury
Interior remodel to units 248, 250a, 250b, 252a & 252b. unit 248: remodel kit, convert living rm to bedrm, add 1-bath & home office; unit 250b: kit & bath remodel; unit 250a & 252a: relocate kit, add laundry, convert kit to office; unit 252b: relocate kit & laundry, remodel bath
- Filed
- Mar 6, 2026
- Issued
- Jul 8, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 15 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 12, 2026 | Mar 5, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 6, 2026 | Mar 6, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Mar 6, 2026 | Apr 29, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 6, 2026 | Apr 28, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Mar 6, 2026 | Apr 17, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 6, 2026 | May 7, 2026 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 6, 2026 | Mar 23, 2026 | Approved |
Building inspector Building Inspection · BID-INSP | Mar 6, 2026 | Jun 15, 2026 | Administrative |
Permit Processing Center Building Inspection · PPC | Mar 6, 2026 | Jun 16, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | May 7, 2026 | May 7, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 2, 2026 | Jun 4, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 2, 2026 | Jun 10, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 2, 2026 | Jun 5, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 2, 2026 | Jun 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 16, 2026 | Jul 8, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $315,000
| Name | Role | License on permit |
|---|---|---|
| My My Ly Mml Architect | Architect | C32972 |
| Tyler Moser Tybret Engineering | Engineer | C84735 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025