121 Dalewood Wy
San Francisco permit 202602246391 · West of Twin Peaks
Convert part of garage into condition space to include (n) bedroom, bathroom, and laundry room. add a window in place of the garage door. curb cut reduction under dpw permit.
- Filed
- Feb 24, 2026
- Issued
- May 11, 2026 (2 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2026 were typically issued within 1 month (median of 3,682 issued permits).
- Review stops
- 12 stops across 5 departments
- Comments issued
- 4 times, by Planning, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 24, 2026 | Feb 24, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 24, 2026 | Feb 24, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 9, 2026 | Mar 9, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 9, 2026 | Mar 9, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 9, 2026 | Mar 9, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 10, 2026 | Mar 10, 2026 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Mar 10, 2026 | Mar 10, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 19, 2026 | Mar 19, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 25, 2026 | Mar 25, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 25, 2026 | Mar 25, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 24, 2026 | May 11, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 11, 2026 | May 11, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $110,000
| Name | Role | License on permit |
|---|---|---|
| Michael Pustov Rpm Team Llc | Engineer | C80452 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2020