San Francisco permit 202602256455 · South of Market

Revision or supplementFull plan reviewIssued

This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.

Street view · Sep 2026
Google Street View of 150 09th St, Sep 2026
Scope of work
As written on the permit application.

Revision to pa #202305026865-s2. revision to miscellaneous in field changed items to previous approved addendum 2 mechanical, electrical and plumbing drawings.

Timeline
Key dates from the city record.
Filed
May 29, 2026
Issued
Aug 12, 2026 (2 months after filing)
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
26 stops across 7 departments
Comments issued
6 times, by Building Inspection
Review stopFinishedResult

Apartment and hotel inspection

Building Inspection · HIS

Feb 25, 2026Approved

Intake

Building Inspection · INTAKE

Feb 25, 2026Administrative

Zoning review

Planning · CP-ZOC

Feb 25, 2026Not Applicable

Public Utilities Commission review

Public Utilities · SFPUC

Feb 25, 2026Not Applicable

Public health review

Public Health · HEALTH

Feb 25, 2026Administrative

Public health food review

Public Health · HEALTH-FD

Feb 25, 2026Not Applicable

Street use and mapping

Public Works · DPW-BSM

Feb 25, 2026Approved

Fire prevention review

Fire Department · SFFD

Feb 27, 2026Approved

Electrical plan review

Building Inspection · MECH-E

Mar 5, 2026Issued Comments

Electrical plan review

Building Inspection · MECH-E

Mar 18, 2026Issued Comments

Permit Center

Permit Center · PERMIT-CTR

May 28, 2026Approved

Central Permit Bureau

Building Inspection · CPB

May 29, 2026Administrative

Mechanical and energy plan review

Building Inspection · MECH

Jun 9, 2026Issued Comments

Electrical plan review

Building Inspection · MECH-E

Jun 4, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Jun 16, 2026Administrative

Street use and mapping

Public Works · DPW-BSM

Jun 4, 2026Approved

Permit Processing Center

Building Inspection · PPC

Jul 29, 2026Administrative

Fire prevention review

Fire Department · SFFD

Jun 16, 2026Not Applicable

Mechanical and energy plan review

Building Inspection · MECH

Jun 29, 2026Issued Comments

Electrical plan review

Building Inspection · MECH-E

Jun 29, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 20, 2026Approved

Electrical plan review

Building Inspection · MECH-E

Jul 22, 2026Approved

Fire prevention review

Fire Department · SFFD

Jul 27, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Jul 27, 2026Approved

Development fee collection

Building Inspection · DFCU

Jul 27, 2026Administrative

Central Permit Bureau

Building Inspection · CPB

Aug 12, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$1
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Daniel M Levine

The John Stewart Company

ArchitectC10154
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202602256455 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record