185 Berry St
San Francisco permit 202602276647 · Mission Bay
Ti for sierra located on levels 1, 5 & 6. selective demo of portion of (e) floor slabs at levels 5 & 6 to create 3 story, interconnected volume intended for "all-hands" assembly gatherings, work also includes construction of stadium-styled seating & associated stairs between level 4, 5 & communicati
- Filed
- Mar 11, 2026
- Issued
- Jun 25, 2026 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 18 stops across 3 departments
- Comments issued
- 6 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 25, 2026 | Mar 10, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 27, 2026 | Mar 12, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Mar 12, 2026 | Apr 30, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 12, 2026 | May 1, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 12, 2026 | Apr 17, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 12, 2026 | Apr 17, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 12, 2026 | Jun 22, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | May 19, 2026 | May 19, 2026 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | May 26, 2026 | May 27, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 27, 2026 | May 27, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 28, 2026 | Jun 1, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 3, 2026 | Jun 18, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 3, 2026 | Jun 3, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jun 3, 2026 | Jun 12, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Jun 3, 2026 | Jun 10, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Jun 16, 2026 | Jun 16, 2026 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Jun 18, 2026 | Jun 22, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jun 22, 2026 | Jun 25, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $2,350,400
| Name | Role | License on permit |
|---|---|---|
| Ariane Lebrilla Asd Sky | Architect | C38312 |
| Scott Fine Arnold Scott Arnold | Engineer | C64169 |
| Michael Paul Gemmill Nabih Youssef Associates | Engineer | 4703 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026