1930 Grove St #3
San Francisco permit 202602276667 · Lone Mountain/USF
Unit 3- remodel (e) kitchen no sturcrtural changes demo selected non structural partitions, new casework, appliances plumbing fixtures and electrical fnishes and lightings.
- Filed
- Feb 27, 2026
- Issued
- May 22, 2026 (3 months after filing)
- Completed
- Sep 16, 2026 (4 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2026 were typically issued within 1 month (median of 3,682 issued permits).
- Review stops
- 6 stops across 2 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Feb 27, 2026 | Feb 27, 2026 | — |
Intake Building Inspection · INTAKE | Feb 27, 2026 | Feb 27, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Feb 27, 2026 | Feb 27, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 27, 2026 | Feb 27, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 27, 2026 | Feb 27, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 22, 2026 | May 22, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $51,144
| Name | Role | License on permit |
|---|---|---|
| Eric D Staten Does Architecture | Architect | C32548 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2022