CheckMyDesigner

3185 Washington St

San Francisco permit 202603026756 · Pacific Heights

Seismic retrofit or foundationFull plan reviewReinstated
Street view · Jan 2025
Google Street View of 3185 Washington St, Jan 2025
Scope of work
As written on the permit application.

Remodel of existing private school building. project includes interior renovation work at basement and level-1 and seismic retrofit work. exterior work includes 2 new fixed fire rated windows at the rear facade, 1 at the first floor and 1 at the basement level

Timeline
Key dates from the city record.
Filed
Mar 18, 2026
Issued
Jul 15, 2026 (4 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 4 departments
Comments issued
6 times, by Building Inspection, Fire Department
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Mar 17, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Mar 19, 2026Administrative

Building plan review

Building Inspection · BLDG

May 7, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

May 14, 2026Administrative

Mechanical and energy plan review

Building Inspection · MECH

Apr 17, 2026Issued Comments

Electrical plan review

Building Inspection · MECH-E

Mar 27, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

May 13, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Apr 8, 2026Approved

Permit Processing Center

Building Inspection · PPC

Jul 9, 2026Administrative

Building plan review

Building Inspection · BLDG

Jul 7, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 5, 2026Approved

Electrical plan review

Building Inspection · MECH-E

Jun 4, 2026Approved

Fire prevention review

Fire Department · SFFD

Jun 9, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jun 4, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Jun 26, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Jun 22, 2026Approved-Stipulated

Mechanical and energy plan review

Building Inspection · MECH

Jul 7, 2026Approved

Electrical plan review

Building Inspection · MECH-E

Jul 7, 2026Approved

Fire prevention review

Fire Department · SFFD

Jul 7, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Jul 8, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 8, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jul 15, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Reinstated
Estimated cost
$4,235,800
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
J Aaron Thornton

Leddy Maytum Stacy Architects

ArchitectC35066
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202603026756 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record