293 Jersey St
San Francisco permit 202603026789 · Noe Valley
2-story horizontal addition at the rear and side. kitchen remodel and new powder room on 2/f. new bedroom and remodeled bathrooms on 3/f. removed powder and enclosed laundry on 1/f. new front door and openings.
- Filed
- Mar 15, 2026
- Issued
- Aug 14, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 19 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 27, 2026 | Mar 10, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 16, 2026 | Mar 16, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 16, 2026 | Mar 17, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 16, 2026 | Apr 28, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 16, 2026 | Apr 27, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Mar 16, 2026 | Apr 12, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 16, 2026 | Mar 27, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 16, 2026 | Mar 19, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 16, 2026 | Mar 30, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 16, 2026 | Jun 8, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 6, 2026 | Apr 6, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 14, 2026 | Apr 22, 2026 | Approved |
Zoning review Planning · CP-ZOC | May 26, 2026 | May 28, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 26, 2026 | Jun 8, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 26, 2026 | Jun 1, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 26, 2026 | May 29, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 26, 2026 | May 28, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 26, 2026 | May 29, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 8, 2026 | Aug 14, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $600,000
| Name | Role | License on permit |
|---|---|---|
| Killian O'sullivan O'sullivan Architecture | Architect | C-30355 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025