100 Stockton St
San Francisco permit 202603036864 · Financial District/South Beach
Core and shell construction of a ground level elevator lobby, addition of a pair of passenger elevators to serve future 3rd floor building tenant.
- Filed
- Apr 30, 2026
- Issued
- Jul 16, 2026 (3 months after filing)
- Completed
- Not completed yet
- Review stops
- 22 stops across 4 departments
- Comments issued
- 5 times, by Planning, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 3, 2026 | Mar 3, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 3, 2026 | Mar 3, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 4, 2026 | Mar 4, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 4, 2026 | Mar 4, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 5, 2026 | Mar 5, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Mar 5, 2026 | Mar 5, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 5, 2026 | Mar 5, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Mar 25, 2026 | Mar 25, 2026 | Approved |
Permit Center Permit Center · PERMIT-CTR | Apr 10, 2026 | Apr 21, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 30, 2026 | Apr 30, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 30, 2026 | May 28, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 30, 2026 | Jun 2, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 30, 2026 | May 27, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 30, 2026 | May 8, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 30, 2026 | May 18, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 30, 2026 | Jul 8, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jul 2, 2026 | Jul 6, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 2, 2026 | Jul 6, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 2, 2026 | Jul 8, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 2, 2026 | Jul 2, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 2, 2026 | Jul 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 8, 2026 | Jul 16, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $2,200,000
| Name | Role | License on permit |
|---|---|---|
| David Joseph Rossi Kpff | Engineer | 4127 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026