1350 Pine St
San Francisco permit 202603046901 · Nob Hill
New adu in basement level of existing 4 story apartment building - includes new living room / kitchen, 1 bedroom, office , and 2 bathrooms
- Filed
- Mar 19, 2026
- Issued
- Jul 14, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 26 stops across 6 departments
- Comments issued
- 9 times, by Planning, Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 26, 2026 | Mar 16, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 16, 2026 | Mar 20, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 20, 2026 | Apr 2, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 20, 2026 | Mar 25, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 20, 2026 | Mar 30, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 20, 2026 | Mar 24, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 20, 2026 | Mar 25, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 20, 2026 | Apr 6, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 20, 2026 | Mar 31, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 20, 2026 | Jul 2, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 26, 2026 | Jun 9, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | May 26, 2026 | May 28, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 26, 2026 | Jun 3, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 26, 2026 | Jun 9, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 26, 2026 | May 28, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 26, 2026 | Apr 8, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 26, 2026 | May 28, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 15, 2026 | Jun 29, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 15, 2026 | Jun 25, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 15, 2026 | Jun 24, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 15, 2026 | Jun 29, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 15, 2026 | Jun 17, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 15, 2026 | Jun 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 15, 2026 | Jun 22, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Jun 29, 2026 | Jun 29, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 2, 2026 | Jul 14, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $275,379
| Name | Role | License on permit |
|---|---|---|
| Richard Parker Hans Vaterlaus Acmr Architectural | Architect | C23212 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026