1 Market St
San Francisco permit 202603046914 · Financial District/South Beach
6/f: interior t.i area of work is 3068 sq.ft partial floor remodel. existing assembly space to be reconfigured. non-structural partition demo. construction of new partitions, doors, and ceiling. mep upgrades and structural.
- Filed
- May 12, 2026
- Issued
- Jul 8, 2026 (2 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 18 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 4, 2026 | Mar 4, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 4, 2026 | Mar 4, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | Mar 4, 2026 | Mar 4, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 4, 2026 | Mar 4, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 4, 2026 | Mar 4, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 6, 2026 | Mar 6, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 6, 2026 | Mar 6, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 24, 2026 | Mar 24, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Mar 24, 2026 | Mar 24, 2026 | Approved |
Permit Center Permit Center · PERMIT-CTR | Apr 7, 2026 | Apr 28, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 29, 2026 | May 12, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | May 12, 2026 | Jun 24, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | May 12, 2026 | May 18, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 12, 2026 | Jun 9, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | May 12, 2026 | May 15, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | May 12, 2026 | Jul 2, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Jun 25, 2026 | Jun 25, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 2, 2026 | Jul 8, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $3,000,000
| Name | Role | License on permit |
|---|---|---|
| Victoria Lynn Salgado | Architect | C37053 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026