80 Bronte St
San Francisco permit 202603057023 · Bernal Heights
Remodel (e) kitchen, living, dining, family rooms and add half bath on 1/f. remodel (e) bedrooms and bathrooms and add bedroom, bath and laundry on 2/f. remodel (e) basement/garage to add bedroom, bath, entry and new stairway.
- Filed
- Apr 2, 2026
- Issued
- Oct 28, 2026 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 23 stops across 5 departments
- Comments issued
- 6 times, by Building Inspection, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 5, 2026 | Mar 5, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 5, 2026 | Mar 5, 2026 | Approved |
Permit Center Permit Center · PERMIT-CTR | Mar 15, 2026 | Apr 1, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 2, 2026 | Apr 2, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 3, 2026 | Apr 7, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 3, 2026 | May 2, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 3, 2026 | May 2, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 3, 2026 | Apr 8, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 3, 2026 | Apr 10, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 3, 2026 | Apr 16, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 3, 2026 | Jul 15, 2026 | Administrative |
Building plan review Building Inspection · BLDG | May 20, 2026 | May 22, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 2, 2026 | Jun 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 2, 2026 | Jun 10, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 2, 2026 | Jun 3, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 2, 2026 | Jun 5, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 2, 2026 | Jun 11, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 11, 2026 | Jul 7, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 11, 2026 | Jun 15, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 11, 2026 | Jun 18, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 11, 2026 | Jun 17, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 11, 2026 | Jun 18, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 17, 2026 | Oct 28, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $685,066
| Name | Role | License on permit |
|---|---|---|
| L A Paul L.A. Paul & Associates | Architect | C8725 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2019