94 Aloha Av
San Francisco permit 202603097137 · Inner Sunset
Vertical & horizontal addition, 3-story expansion focused on rear yard across both levels, front facade updated finishes, new windows, new bay window addition, landscape & drainage- water-reistant landscape will enhance erosion control, deep root systems & new drainage system. 2/f & 3/f rear balcony
- Filed
- Apr 15, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 34 stops across 6 departments
- Comments issued
- 7 times, by Permit Center, Planning, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 5, 2026 | Mar 19, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 1, 2026 | Apr 15, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 15, 2026 | Apr 16, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 16, 2026 | Apr 30, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 16, 2026 | May 30, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 16, 2026 | May 30, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 16, 2026 | May 27, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 16, 2026 | Apr 20, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 16, 2026 | Apr 20, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 16, 2026 | May 17, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 16, 2026 | May 1, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 16, 2026 | Aug 19, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Apr 23, 2026 | Apr 23, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 24, 2026 | Apr 28, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 24, 2026 | Apr 27, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 29, 2026 | May 4, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 1, 2026 | May 1, 2026 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | May 4, 2026 | May 13, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 4, 2026 | May 5, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 4, 2026 | May 6, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 4, 2026 | May 8, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jul 13, 2026 | Jul 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 13, 2026 | Aug 3, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 13, 2026 | Jul 14, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 13, 2026 | Jul 14, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jul 13, 2026 | Jul 15, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 13, 2026 | Aug 11, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 13, 2026 | Jul 16, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jul 31, 2026 | Aug 4, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 31, 2026 | Aug 5, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 31, 2026 | Aug 3, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jul 31, 2026 | Aug 5, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 31, 2026 | Aug 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 19, 2026 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $909,723
| Name | Role | License on permit |
|---|---|---|
| Edmond Wong Ekw Engineering | Engineer | C86522 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025