2952 Folsom St
San Francisco permit 202603117341 · Mission
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revise approved adu pa# 201910083942. revise adus# 1 & @ adn add adu# 3. addition of adu pursuant to planning code section 207.1.
- Filed
- Mar 24, 2026
- Issued
- Jun 16, 2026 (3 months after filing)
- Completed
- Not completed yet
- Review stops
- 20 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department, Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 4, 2026 | Mar 23, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 24, 2026 | Mar 24, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 24, 2026 | Mar 25, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 24, 2026 | Apr 17, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 24, 2026 | Apr 15, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Mar 24, 2026 | Apr 17, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 24, 2026 | Apr 1, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 24, 2026 | Mar 26, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 24, 2026 | Jun 4, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 24, 2026 | Mar 24, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 24, 2026 | Jun 9, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 25, 2026 | Mar 25, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | May 14, 2026 | May 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 14, 2026 | May 26, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 14, 2026 | May 18, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 14, 2026 | May 20, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 14, 2026 | May 18, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 14, 2026 | May 19, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Jun 5, 2026 | Jun 9, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jun 9, 2026 | Jun 16, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $280,000
| Name | Role | License on permit |
|---|---|---|
| My My Ly Mml Architect | Architect | C32972 |
| Engin Yagmur Ecr Engineering | Engineer | 76016 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026