255 Bocana St
San Francisco permit 202603117355 · Bernal Heights
Remodel entire home to include remodel of (1) kitchen and 2 bathroom remodel and include (n) bathroom. new exterior stair from (e) deck to grade. no additional square footage or change to footprint.
- Filed
- Jun 22, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 28 stops across 5 departments
- Comments issued
- 8 times, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 11, 2026 | Mar 11, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 8, 2026 | Apr 8, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | May 1, 2026 | May 1, 2026 | Approved |
Permit Center Permit Center · PERMIT-CTR | May 21, 2026 | Jun 8, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 9, 2026 | Jun 22, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 22, 2026 | Jun 24, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 22, 2026 | Aug 18, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 22, 2026 | Aug 14, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 22, 2026 | Jul 17, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 22, 2026 | Jun 29, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 22, 2026 | Jul 9, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 22, 2026 | In progress | — |
Zoning review Planning · CP-ZOC | Aug 24, 2026 | Aug 24, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 24, 2026 | Aug 28, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 31, 2026 | Aug 31, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 1, 2026 | Sep 1, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 12, 2026 | Sep 15, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 18, 2026 | Sep 18, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 22, 2026 | Sep 22, 2026 | Approved |
Zoning review Planning · CP-ZOC | Oct 1, 2026 | Oct 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 1, 2026 | Oct 13, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 1, 2026 | Oct 5, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Oct 19, 2026 | Oct 21, 2026 | Approved |
Zoning review Planning · CP-ZOC | Oct 20, 2026 | Oct 20, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 27, 2026 | Oct 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | Nov 3, 2026 | Nov 4, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Lauren Marie Wingert Lauren Wingert | Engineer | C80032 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025