2739 Geary Bl
San Francisco permit 202603127455 · Lone Mountain/USF
Front building: conversion of (e) partial 2nd floor to accommodate 1 new adu unit per state adu program.
- Filed
- Mar 25, 2026
- Issued
- Oct 20, 2026 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 25 stops across 6 departments
- Comments issued
- 6 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 9, 2026 | Mar 25, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 26, 2026 | Mar 26, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 26, 2026 | May 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 26, 2026 | Apr 20, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 26, 2026 | Apr 3, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Mar 26, 2026 | Apr 1, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 26, 2026 | May 18, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 26, 2026 | May 17, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 26, 2026 | Apr 3, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 26, 2026 | Oct 1, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | May 13, 2026 | May 13, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 14, 2026 | May 14, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 15, 2026 | May 19, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 22, 2026 | May 22, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 22, 2026 | Jul 22, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 27, 2026 | Jul 27, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 28, 2026 | Jul 28, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 28, 2026 | Jul 28, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Aug 14, 2026 | Aug 14, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Aug 19, 2026 | Sep 9, 2026 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Sep 9, 2026 | Sep 29, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 9, 2026 | Oct 1, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Oct 1, 2026 | Oct 1, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 1, 2026 | Oct 20, 2026 | Administrative |
Address verification Building Inspection · ADDR | Oct 13, 2026 | Oct 13, 2026 | Not Applicable |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $69,357
| Name | Role | License on permit |
|---|---|---|
| Rod Massoudi Massoudi Consulting Engineer | Engineer | C81412 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026