Front building: conversion of (e) partial 2nd floor to accommodate 1 new adu unit per state adu program.

Timeline
Key dates from the city record.
Filed
Mar 25, 2026
Issued
Oct 20, 2026 (7 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
25 stops across 6 departments
Comments issued
6 times, by Building Inspection, Fire Department
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Mar 25, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Mar 26, 2026Administrative

Zoning review

Planning · CP-ZOC

May 5, 2026Approved

Building plan review

Building Inspection · BLDG

Apr 20, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 3, 2026Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Apr 1, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

May 18, 2026Approved

Urban forestry

Public Works · DPW-BUF

May 17, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 3, 2026Approved

Permit Processing Center

Building Inspection · PPC

Oct 1, 2026Administrative

Fire Department housing review

Fire Department · SFFD-HQ

May 13, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

May 14, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

May 19, 2026Approved

Building plan review

Building Inspection · BLDG

May 22, 2026Issued Comments

Building plan review

Building Inspection · BLDG

Jul 22, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Jul 27, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 28, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 28, 2026Approved

Fire Department housing review

Fire Department · SFFD-HQ

Aug 14, 2026Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Sep 9, 2026Approved-Stipulated

Zoning review

Planning · CP-ZOC

Sep 29, 2026Approved

Urban forestry

Public Works · DPW-BUF

Oct 1, 2026Approved

Development fee collection

Building Inspection · DFCU

Oct 1, 2026Administrative

Central Permit Bureau

Building Inspection · CPB

Oct 20, 2026Administrative

Address verification

Building Inspection · ADDR

Oct 13, 2026Not Applicable

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$69,357
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Rod Massoudi

Massoudi Consulting Engineer

EngineerC81412
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202603127455 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record