4174 26th St

San Francisco permit 202603167636 · Noe Valley

AdditionFull plan reviewIssued
Street view · Mar 2025
Google Street View of 4174 26th St, Mar 2025
Scope of work
As written on the permit application.

Scope of work to include adding a new floor to existing single family dwelling to consist of a new primary bedroom, bathroom, closet, and a modest north deck.

Timeline
Key dates from the city record.
Filed
Apr 28, 2026
Issued
Aug 31, 2026 (4 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
23 stops across 6 departments
Comments issued
7 times, by Permit Center, Building Inspection, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Apr 1, 2026Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Apr 27, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Apr 29, 2026Administrative

Zoning review

Planning · CP-ZOC

May 5, 2026Approved

Building plan review

Building Inspection · BLDG

Jun 29, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 26, 2026Not Applicable

Mechanical and energy plan review

Building Inspection · MECH

May 30, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

May 1, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

May 6, 2026Issued Comments

Urban forestry

Public Works · DPW-BUF

Jun 9, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

May 19, 2026Approved

Permit Processing Center

Building Inspection · PPC

Aug 21, 2026Administrative

Building plan review

Building Inspection · BLDG

Jul 13, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 14, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jul 22, 2026Approved

Urban forestry

Public Works · DPW-BUF

Aug 11, 2026Approved

Building plan review

Building Inspection · BLDG

Jul 31, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 28, 2026Approved

Fire prevention review

Fire Department · SFFD

Aug 4, 2026Approved-Stipulated

Zoning review

Planning · CP-ZOC

Aug 19, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Aug 20, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 17, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Aug 31, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$453,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Andrew Johnston Rodgers

Rodgers Architecture

ArchitectC30697
Shaun Edward Moynahan

Semco Engineering

EngineerS4605
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202603167636 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record