1347 40th Av
San Francisco permit 202603167679 · Sunset/Parkside
Convert existing conditioned space on street level to adu.
- Filed
- Apr 14, 2026
- Issued
- May 29, 2026 (1 month after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 26 stops across 6 departments
- Comments issued
- 4 times, by Permit Center, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 13, 2026 | Mar 27, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Mar 31, 2026 | Apr 14, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 14, 2026 | Apr 14, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 14, 2026 | Apr 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 14, 2026 | Apr 17, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 14, 2026 | Apr 23, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 14, 2026 | Apr 22, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 14, 2026 | Apr 15, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Apr 14, 2026 | Apr 16, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 14, 2026 | Apr 28, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 14, 2026 | Apr 17, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 14, 2026 | May 21, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 15, 2026 | Apr 16, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 29, 2026 | Apr 29, 2026 | Approved |
Zoning review Planning · CP-ZOC | May 4, 2026 | May 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 4, 2026 | May 15, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 4, 2026 | May 20, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 4, 2026 | May 13, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 4, 2026 | May 6, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 4, 2026 | May 14, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 4, 2026 | May 18, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 4, 2026 | May 6, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 6, 2026 | May 7, 2026 | Approved |
Development fee collection Building Inspection · DFCU | May 20, 2026 | May 20, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 21, 2026 | May 29, 2026 | Administrative |
Address verification Building Inspection · ADDR | May 28, 2026 | May 28, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $185,000
| Name | Role | License on permit |
|---|---|---|
| Michael L Tauber Michael Tauber Architecture | Architect | C25947 |
| Gregory Paul Wallace Gregory Paul Wallace Struct | Engineer | S3308 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2014