San Francisco permit 202603177728 · Sunset/Parkside

Home remodel (type unconfirmed)Full plan reviewIssued
Street view · Jul 2015
Google Street View of 1988 21st Av, Jul 2015
Scope of work
As written on the permit application.

Remodel bldg layout by demo e) walls & provide n) structural support. add 2 bedrm & 2 baths to g/f. enclose e) stair area to const a n) interior staircase, install a n) skylight, replace e) ground fl windows w/ n) glazed sliding doors, rewire electrical system & install n) lighting & outlet

Timeline
Key dates from the city record.
Filed
Apr 23, 2026
Issued
Aug 26, 2026 (4 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
28 stops across 5 departments
Comments issued
4 times, by Building Inspection, Fire Department
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Mar 17, 2026Administrative

Zoning review

Planning · CP-ZOC

Mar 17, 2026Approved

Permit Center

Permit Center · PERMIT-CTR

Apr 10, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Apr 27, 2026Administrative

Zoning review

Planning · CP-ZOC

Apr 29, 2026Approved

Building plan review

Building Inspection · BLDG

Jun 21, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 20, 2026Administrative

Mechanical and energy plan review

Building Inspection · MECH

May 21, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 29, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

May 13, 2026Approved

Permit Processing Center

Building Inspection · PPC

Aug 21, 2026Administrative

Mechanical and energy plan review

Building Inspection · MECH

Jul 14, 2026Approved

Zoning review

Planning · CP-ZOC

Jul 15, 2026Approved

Fire prevention review

Fire Department · SFFD

Jul 22, 2026Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Jul 16, 2026Approved

Fire prevention review

Fire Department · SFFD

Jul 23, 2026Approved

Building plan review

Building Inspection · BLDG

Jul 28, 2026Issued Comments

Zoning review

Planning · CP-ZOC

Aug 5, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 10, 2026Approved

Building plan review

Building Inspection · BLDG

Aug 12, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 19, 2026Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Aug 13, 2026Approved

Zoning review

Planning · CP-ZOC

Aug 17, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 18, 2026Approved

Fire prevention review

Fire Department · SFFD

Aug 19, 2026Approved

Building plan review

Building Inspection · BLDG

Aug 20, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 21, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Aug 26, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$599,698
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Jeff Chow

Avenyr

EngineerC81252
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202603177728 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record