125 Alma St
San Francisco permit 202603187803 · Haight Ashbury
Addition to existing 3rd floor to remodel existing rooms & add new bedroom and balcony.
- Filed
- Apr 13, 2026
- Issued
- Oct 5, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 28 stops across 6 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 16, 2026 | Apr 3, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 6, 2026 | Apr 15, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 15, 2026 | Apr 16, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 15, 2026 | Jun 4, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 15, 2026 | Jun 9, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 15, 2026 | Jun 8, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 15, 2026 | May 1, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 15, 2026 | Apr 16, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 15, 2026 | Apr 22, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 15, 2026 | May 28, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 15, 2026 | May 6, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 15, 2026 | Sep 14, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | May 7, 2026 | May 7, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 7, 2026 | Aug 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 7, 2026 | Aug 20, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 7, 2026 | Aug 10, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 7, 2026 | Aug 20, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 7, 2026 | Aug 10, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 7, 2026 | Aug 24, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 7, 2026 | Aug 10, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 31, 2026 | Sep 9, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 31, 2026 | Sep 3, 2026 | Approved |
Zoning review Planning · CP-ZOC | Sep 1, 2026 | Sep 1, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 2, 2026 | Sep 2, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 9, 2026 | Sep 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 9, 2026 | Sep 10, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 9, 2026 | Sep 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 14, 2026 | Oct 5, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Jefferson Chen Enertia Designs | Engineer | C57898 |
| L A Paul L.A. Paul & Associates | Architect | C8725 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026