451 Pacific Av
San Francisco permit 202603187866 · Chinatown
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to core & shell pa# 202505126265: framing detail @ level 3 elevator penthouse, elevator shaft structural framing, structural strengthening at level 3 underside of north & south roof, modification to restroom at level 2 mezzanine, a switch from a prefabication metal stair to a pre-fab wood
- Filed
- May 18, 2026
- Issued
- Sep 2, 2026 (4 months after filing)
- Completed
- Not completed yet
- Review stops
- 25 stops across 5 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 18, 2026 | Mar 18, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 1, 2026 | Apr 1, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 1, 2026 | Apr 1, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 10, 2026 | Apr 10, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 24, 2026 | Apr 24, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 27, 2026 | Apr 27, 2026 | Approved-Stipulated |
Permit Center Permit Center · PERMIT-CTR | May 5, 2026 | May 15, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 19, 2026 | May 19, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 19, 2026 | May 21, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 19, 2026 | Jul 24, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 19, 2026 | Jul 7, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | May 19, 2026 | Jun 4, 2026 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | May 19, 2026 | Jun 5, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | May 19, 2026 | Aug 31, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jun 23, 2026 | Jul 29, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 20, 2026 | Aug 31, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 20, 2026 | Aug 25, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 20, 2026 | Aug 20, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 20, 2026 | Aug 24, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 20, 2026 | Aug 28, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 26, 2026 | Aug 26, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 26, 2026 | Aug 26, 2026 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Aug 28, 2026 | Aug 28, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 28, 2026 | Aug 28, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 31, 2026 | Sep 2, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| Michael Joseph Castro Michael Castro | Architect | C24073 |
| Alan Charles Burr Murphy Burr Curry | Engineer | S5062 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026