3829 25th St
San Francisco permit 202603258227 · Noe Valley
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to permit 202506077833: add covered entry over front door, add balcony @ 3rd flr bedroom,modify kitchen & entry layout, additional area of foundation replacement & detail clarification. rooftop hot tub.
- Filed
- May 20, 2026
- Issued
- Nov 3, 2026 (5 months after filing)
- Completed
- Not completed yet
- Review stops
- 18 stops across 6 departments
- Comments issued
- 3 times, by Fire Department, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 22, 2026 | Apr 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 9, 2026 | May 20, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 20, 2026 | Jun 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 20, 2026 | Jun 18, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 20, 2026 | Jun 18, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 20, 2026 | Jul 2, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 20, 2026 | May 22, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 20, 2026 | May 21, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 20, 2026 | Jun 26, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 20, 2026 | May 21, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | May 20, 2026 | Sep 10, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | May 22, 2026 | May 22, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 10, 2026 | Aug 10, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 11, 2026 | Aug 11, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Aug 11, 2026 | Aug 12, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 3, 2026 | Sep 3, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Sep 3, 2026 | Sep 3, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 10, 2026 | Nov 3, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $10,000
| Name | Role | License on permit |
|---|---|---|
| Troy A Kashanipour Troy Kashanipour | Architect | C27646 |
| Joe Terhemen Igber Sedr Consulting | Engineer | C78132 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025