769 A Clayton St
San Francisco permit 202603278465 · Haight Ashbury
1. remodel (e) garden apartment. 2. reconfigure/rebuild (e) ground floor deck. 3. reconfigure (e) ground floor garage and utility area to provide dedicated shared laundry. 4. voluntary replacement of portion of (e) perimeter foundation. 5. no work at (e) primary dwelling (second and third floor).
- Filed
- Apr 16, 2026
- Issued
- Sep 28, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 22 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 26, 2026 | Apr 7, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 15, 2026 | May 13, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 13, 2026 | May 14, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 13, 2026 | Jul 20, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 13, 2026 | Jul 20, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | May 13, 2026 | Jun 11, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 13, 2026 | May 18, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | May 13, 2026 | May 26, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | May 13, 2026 | Sep 16, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Jul 17, 2026 | Jul 17, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 17, 2026 | Aug 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 17, 2026 | Aug 28, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 17, 2026 | Aug 25, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 17, 2026 | Aug 18, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 17, 2026 | Aug 18, 2026 | Approved |
Zoning review Planning · CP-ZOC | Sep 2, 2026 | Sep 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 2, 2026 | Sep 8, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 2, 2026 | Sep 16, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 2, 2026 | Sep 3, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Sep 2, 2026 | Sep 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 16, 2026 | Sep 28, 2026 | Administrative |
Address verification Building Inspection · ADDR | Sep 25, 2026 | Sep 25, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Jared Mark Kuykendall Studio 797 Architecture | Architect | C36856 |
| Donald David Double D Engineering | Engineer | S3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024