216 Ward St
San Francisco permit 202603308500 · Portola
Legalize ground floor unit as adu and to abate nov# 202545522, construct non-load bearing paritition and new fire rated partition, modification to ceilings, ground, lighting, mechanical, plumbing, window modification, add new 100 amp sub panel, add new electric heat pump mini-split. adu ca state.
- Filed
- Apr 8, 2026
- Issued
- Aug 19, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 30 stops across 6 departments
- Comments issued
- 8 times, by Planning, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 26, 2026 | Apr 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 6, 2026 | Apr 8, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 8, 2026 | Apr 13, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 8, 2026 | Apr 13, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 8, 2026 | Apr 20, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 8, 2026 | Apr 15, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Apr 8, 2026 | Apr 10, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 8, 2026 | Apr 13, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 8, 2026 | Apr 16, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 8, 2026 | Apr 15, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 8, 2026 | Jul 14, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 28, 2026 | Jun 16, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | May 28, 2026 | Jun 10, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 28, 2026 | Jun 11, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 28, 2026 | Jun 5, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | May 28, 2026 | May 31, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 28, 2026 | Jun 1, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 28, 2026 | Jun 16, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 28, 2026 | Jun 8, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 26, 2026 | Jul 9, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 26, 2026 | Jul 1, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 26, 2026 | Jul 6, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 26, 2026 | Jul 7, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Jun 26, 2026 | Jun 29, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jun 26, 2026 | Jul 2, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 26, 2026 | Jul 13, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 26, 2026 | Jul 6, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Jul 14, 2026 | Jul 14, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 14, 2026 | Aug 19, 2026 | Administrative |
Address verification Building Inspection · ADDR | Jul 17, 2026 | Jul 17, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $105,274
| Name | Role | License on permit |
|---|---|---|
| Benjamin Louie Sunset & Annex Inc | Architect | C37813 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025