3666 Baker St
San Francisco permit 202604018654 · Marina
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to 202305037030 to remove office and change family room to gym. expand media room & add wet bar. (n) horizontal addition to include roof deck and entry to hall and laundry room. (n) sprial stair to roof deck. remodel interior stair. (n) update kitchen, bath 1 , 2 ref 202412197150
- Filed
- Jun 16, 2026
- Issued
- Oct 9, 2026 (4 months after filing)
- Completed
- Not completed yet
- Review stops
- 27 stops across 7 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 1, 2026 | Apr 1, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 1, 2026 | Apr 1, 2026 | Approved |
Permit Center Permit Center · PERMIT-CTR | May 28, 2026 | Jun 15, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 16, 2026 | Jun 16, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 17, 2026 | Jun 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 17, 2026 | Aug 14, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 17, 2026 | Aug 18, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 17, 2026 | Jul 23, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 17, 2026 | Jul 1, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 17, 2026 | Jun 18, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jun 17, 2026 | Aug 19, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 17, 2026 | Jun 24, 2026 | Approved |
Public Health HEALTH-MH | Jun 17, 2026 | Jun 18, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 17, 2026 | Oct 2, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 4, 2026 | Sep 4, 2026 | Approved |
Public Health HEALTH-MH | Sep 4, 2026 | Sep 4, 2026 | Approved |
Zoning review Planning · CP-ZOC | Sep 8, 2026 | Sep 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 8, 2026 | Sep 21, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 8, 2026 | Sep 15, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2026 | Sep 10, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 8, 2026 | Sep 18, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 8, 2026 | Sep 14, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 8, 2026 | Sep 29, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 8, 2026 | Sep 11, 2026 | Approved |
Public Health HEALTH-MH | Sep 8, 2026 | Sep 9, 2026 | Not Applicable |
Urban forestry Public Works · DPW-BUF | Oct 2, 2026 | Oct 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 2, 2026 | Oct 9, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $144,276
| Name | Role | License on permit |
|---|---|---|
| Aaron Michael Lim Aaron Lim Design | Architect | C37034 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023