1828 Egbert Av
San Francisco permit 202604089073 · Bayview Hunters Point
Ref#: 202412317576. work consisting of contructing new 4 stop freight elevator in existing shaf. 2hr rated shaft walls plus 2 new 2 hr rated shaft walls to creat the 4 sided shaft enclosure. project scope includes cutting into the (e) mat foundation to create the elevator pit, plus new steel
- Filed
- Apr 8, 2026
- Issued
- Oct 19, 2026 (6 months after filing)
- Completed
- Not completed yet
- Review stops
- 19 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 8, 2026 | Apr 8, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 8, 2026 | Apr 8, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | Apr 8, 2026 | Apr 8, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 8, 2026 | Apr 8, 2026 | Issued Comments |
Public Works disability access review Public Works · PW-DAC | Apr 8, 2026 | Apr 8, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 9, 2026 | Apr 9, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 9, 2026 | Apr 9, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 14, 2026 | Apr 14, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 14, 2026 | Apr 14, 2026 | Approved-Stipulated |
Electrical plan review Building Inspection · MECH-E | Apr 14, 2026 | Apr 14, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 15, 2026 | Apr 15, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 15, 2026 | Apr 15, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 15, 2026 | Apr 15, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 15, 2026 | Apr 15, 2026 | Not Applicable |
Intake Building Inspection · INTAKE | Oct 14, 2026 | Oct 14, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Oct 14, 2026 | Oct 14, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 15, 2026 | Oct 15, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Oct 19, 2026 | Oct 19, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 19, 2026 | Oct 19, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $700,000
| Name | Role | License on permit |
|---|---|---|
| Ivan Romero | Architect | C12045 |
| Raymond Lui Sfdpw | Engineer | S4094 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026