2300 Harrison St
San Francisco permit 202604139302 · Mission
New gender neutral resterooms - demo, new partitions, ceilings, and finishes.
- Filed
- Apr 13, 2026
- Issued
- May 6, 2026 (within 1 month of filing)
- Completed
- Jul 7, 2026 (2 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2026 were typically issued within 1 month (median of 3,682 issued permits).
- Review stops
- 7 stops across 3 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 13, 2026 | Apr 13, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 13, 2026 | Apr 13, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | Apr 13, 2026 | Apr 13, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | May 1, 2026 | May 1, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 5, 2026 | May 5, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | May 5, 2026 | May 5, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 6, 2026 | May 6, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Victoria Lynn Salgado | Architect | C37053 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026