1619 43rd Av
San Francisco permit 202604139317 · Sunset/Parkside
Partial conversion of existing garage into habitable space, including a bedroom, sitting area, office, and bathroom. maintain 20' deep garage. construction of a new deck of the primary bedroom on the main floor. replace existing single pane aluminum windows at the rear of the house on the main floor
- Filed
- May 28, 2026
- Issued
- Oct 27, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 22 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 10, 2026 | Apr 27, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 27, 2026 | May 28, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 28, 2026 | Jun 1, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 28, 2026 | Jul 22, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 28, 2026 | Jul 22, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | May 28, 2026 | Jun 21, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 28, 2026 | Jun 10, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 28, 2026 | Jun 11, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | May 28, 2026 | Sep 29, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jun 21, 2026 | Jun 21, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Jul 22, 2026 | Jul 22, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 13, 2026 | Aug 13, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 13, 2026 | Aug 26, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 13, 2026 | Aug 20, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 13, 2026 | Aug 24, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 13, 2026 | Aug 14, 2026 | Approved |
Zoning review Planning · CP-ZOC | Sep 8, 2026 | Sep 8, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 8, 2026 | Sep 22, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2026 | Sep 10, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 8, 2026 | Sep 18, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 8, 2026 | Sep 10, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 29, 2026 | Oct 27, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $120,000
| Name | Role | License on permit |
|---|---|---|
| Aws Salahaldin Aaa Engineering Design | Engineer | C95446 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2017