61 Royal Ln
San Francisco permit 202604139320 · Excelsior
Erect 3-story, type 5b, single fmily residence with adu.
- Filed
- Jun 6, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 24 stops across 6 departments
- Comments issued
- 6 times, by Permit Center, Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 10, 2026 | Apr 21, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 18, 2026 | Jun 3, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 4, 2026 | Jun 8, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 8, 2026 | Jun 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 8, 2026 | Jul 6, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jun 8, 2026 | Jun 18, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 8, 2026 | Jun 16, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jun 8, 2026 | Jul 28, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 8, 2026 | Jul 1, 2026 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jun 8, 2026 | Jul 10, 2026 | Approved |
Address verification Building Inspection · ADDR | Jun 8, 2026 | In progress | — |
Permit Processing Center Building Inspection · PPC | Jun 8, 2026 | In progress | — |
Address verification Building Inspection · ADDR | Jun 24, 2026 | Jun 24, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Jul 21, 2026 | Jul 21, 2026 | Approved |
Zoning review Planning · CP-ZOC | Oct 27, 2026 | Oct 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 27, 2026 | In progress | — |
Fire Department housing review Fire Department · SFFD-HQ | Oct 27, 2026 | Oct 30, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 27, 2026 | Oct 27, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Oct 27, 2026 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 27, 2026 | Oct 28, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Oct 27, 2026 | Oct 30, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Filed
- Estimated cost
- $600,000
| Name | Role | License on permit |
|---|---|---|
| Yang Nie Nie Yang Architects | Architect | C31413 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022