1263 33rd Av
San Francisco permit 202604139328 · Sunset/Parkside
Bring udu into compliance nov202545325: build rated wall between garage and hall from front door to udu; building btw hall and furnace and water heater; verify (e) insulation; upgrade floor/ceiling assembly to 1hr fire rating. upgrade back walll seismically to account for new sliding glass door.
- Filed
- Aug 12, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 22 stops across 6 departments
- Comments issued
- 9 times, by Permit Center, Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 10, 2026 | Apr 21, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jun 10, 2026 | Jul 1, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jul 25, 2026 | Aug 11, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 12, 2026 | Aug 13, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 13, 2026 | Aug 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 13, 2026 | Aug 17, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 13, 2026 | Aug 28, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 13, 2026 | Aug 19, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 13, 2026 | Aug 19, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 13, 2026 | Sep 1, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 13, 2026 | Aug 26, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 13, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Aug 17, 2026 | Sep 1, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 27, 2026 | Aug 27, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 2, 2026 | Sep 2, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $60,000
| Name | Role | License on permit |
|---|---|---|
| David Scott Locicero David Locicero | Architect | C19452 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025