2450 Van Ness Av
San Francisco permit 202604149350 · Russian Hill
Convert g/f t o2 new residential units. renovate 2nd flor unit #201.
- Filed
- Jun 2, 2026
- Issued
- Oct 9, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 20 stops across 6 departments
- Comments issued
- 3 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 10, 2026 | Apr 23, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 19, 2026 | Jun 1, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 2, 2026 | Jun 2, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 2, 2026 | Jun 16, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 2, 2026 | Jul 23, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 2, 2026 | Jul 23, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 2, 2026 | Jun 18, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 2, 2026 | Jul 28, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 2, 2026 | Jun 23, 2026 | Approved |
Public Health HEALTH-MH | Jun 2, 2026 | Jun 12, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 2, 2026 | Oct 2, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2026 | Sep 8, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 15, 2026 | Sep 15, 2026 | Approved |
Zoning review Planning · CP-ZOC | Sep 16, 2026 | Sep 30, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 16, 2026 | Oct 1, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 16, 2026 | Sep 25, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 16, 2026 | Sep 17, 2026 | Approved |
Public Health HEALTH-MH | Sep 16, 2026 | Sep 21, 2026 | Not Applicable |
Development fee collection Building Inspection · DFCU | Oct 1, 2026 | Oct 1, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 2, 2026 | Oct 9, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $260,000
| Name | Role | License on permit |
|---|---|---|
| Gregory K Iboshi Huang Iboshi Architecture | Architect | C-27547 |
| Donald David Double D Engineering | Engineer | S3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2025