4232 25th St
San Francisco permit 202604169600 · Noe Valley
Convert part of detached garage into adu (state program), with 1-bedroom unit with kitchen and bathroom. (n) unit to be provided with nfpa13r automatic fire sprinkler system under separate permit. fire alarm under separate permit.
- Filed
- Jun 14, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 24 stops across 6 departments
- Comments issued
- 5 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 12, 2026 | Apr 24, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 23, 2026 | Jun 8, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 10, 2026 | Jun 15, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 15, 2026 | Jun 29, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 15, 2026 | Jun 23, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 15, 2026 | Jun 22, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 15, 2026 | Jun 23, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 15, 2026 | Jun 29, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 15, 2026 | Jun 18, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jun 15, 2026 | Jul 1, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 15, 2026 | Jun 29, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 15, 2026 | Sep 9, 2026 | Administrative |
Address verification Building Inspection · ADDR | Jun 17, 2026 | Aug 25, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 19, 2026 | Sep 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 19, 2026 | Aug 24, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 19, 2026 | Aug 25, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 19, 2026 | Aug 31, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 19, 2026 | Sep 9, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 19, 2026 | Aug 26, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Aug 19, 2026 | Sep 4, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 19, 2026 | Aug 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 9, 2026 | Sep 9, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Sep 9, 2026 | Sep 9, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 9, 2026 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $350,000
| Name | Role | License on permit |
|---|---|---|
| John Taylor Hood Janes Street Architects | Architect | C14187 |
| Donald David Double D Enginneering, Inc | Engineer | 3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025