CheckMyDesigner

657 Arguello Bl

San Francisco permit 202604219801 · Inner Richmond

AdditionFull plan reviewIssued
Street view · May 2025
Google Street View of 657 Arguello Bl, May 2025
Scope of work
As written on the permit application.

Horizontal addition and new 3rd flr expanision; expansion of conditined living space to 1/f with new bedroom, bath, exercise & media room; reconfigure 2/f with living/dining, kitchen, bath & study; & new 3/f with 3-bedrooms & 2-baths.

Timeline
Key dates from the city record.
Filed
May 7, 2026
Issued
Sep 8, 2026 (4 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 6 departments
Comments issued
5 times, by Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

May 6, 2026Approved

Central Permit Bureau

Building Inspection · CPB

May 7, 2026Administrative

Zoning review

Planning · CP-ZOC

May 11, 2026Approved

Building plan review

Building Inspection · BLDG

Jul 22, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jul 7, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jun 6, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

May 12, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

May 21, 2026Issued Comments

Urban forestry

Public Works · DPW-BUF

Jun 11, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 28, 2026Approved

Permit Processing Center

Building Inspection · PPC

Aug 25, 2026Administrative

Street use and mapping

Public Works · DPW-BSM

Jun 3, 2026Approved

Zoning review

Planning · CP-ZOC

Aug 13, 2026Approved

Building plan review

Building Inspection · BLDG

Aug 14, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Aug 14, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 18, 2026Approved

Fire prevention review

Fire Department · SFFD

Aug 13, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Aug 17, 2026Approved

Urban forestry

Public Works · DPW-BUF

Aug 17, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 17, 2026Approved

Development fee collection

Building Inspection · DFCU

Aug 25, 2026Administrative

Central Permit Bureau

Building Inspection · CPB

Sep 8, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$802,109
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Mark Jeffrey Topetcher

Topetcher Architectural

ArchitectC21678
Colm O Suilleabhain

Benchmark Engineering

EngineerC93697
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202604219801 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record