801 Wisconsin St
San Francisco permit 202604229851 · Potrero Hill
Remodel of (e) bathroom and new second guest bathroom (e) partition and door. (n) non structural partitions. (n) 100 am sub panel, (n) ducted heat pump system on l2. replace rear siding.replace 2 (e) skylights .
- Filed
- Apr 22, 2026
- Issued
- May 8, 2026 (within 1 month of filing)
- Completed
- Sep 8, 2026 (4 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2026 were typically issued within 1 month (median of 3,682 issued permits).
- Review stops
- 11 stops across 3 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 22, 2026 | Apr 22, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 22, 2026 | Apr 22, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | Apr 22, 2026 | Apr 22, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 22, 2026 | Apr 22, 2026 | Approved |
Intake Building Inspection · INTAKE | May 7, 2026 | May 7, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 7, 2026 | May 7, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | May 7, 2026 | May 7, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 8, 2026 | May 8, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 8, 2026 | May 8, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 8, 2026 | May 8, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 8, 2026 | May 8, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $60,000
| Name | Role | License on permit |
|---|---|---|
| Casey Burdett Ramirez Caha Design Group | Architect | C40159 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025