1879 45th Av
San Francisco permit 202604229866 · Sunset/Parkside
Floor 1- partially demo (e) concrete slab and lower to achieve 7'-6" clear head height. construct rear yard addition to accomodate (n) kitchen and dining room. construct (n) interior staircase to floor 2. remodel interior to accomodate (n) bathroom, family room, mechanical room, and storage. floor 2
- Filed
- May 28, 2026
- Issued
- Oct 5, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 26 stops across 6 departments
- Comments issued
- 6 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 22, 2026 | Apr 22, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 22, 2026 | Apr 22, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 23, 2026 | Apr 23, 2026 | Denied |
Permit Center Permit Center · PERMIT-CTR | Apr 28, 2026 | May 19, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 20, 2026 | May 28, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 28, 2026 | Jun 11, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 28, 2026 | Jul 23, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 28, 2026 | Jul 23, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 28, 2026 | Jun 27, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 28, 2026 | Jun 5, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 28, 2026 | Jun 1, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | May 28, 2026 | Jul 8, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 28, 2026 | Jun 8, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | May 28, 2026 | Sep 10, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Jun 26, 2026 | Jul 7, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 8, 2026 | Jul 8, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 4, 2026 | Aug 4, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 4, 2026 | Aug 5, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Aug 5, 2026 | Aug 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 10, 2026 | Aug 10, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 10, 2026 | Aug 10, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 11, 2026 | Aug 11, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 24, 2026 | Aug 24, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 26, 2026 | Sep 2, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 26, 2026 | Sep 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 10, 2026 | Oct 5, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $217,000
| Name | Role | License on permit |
|---|---|---|
| David Townsend Brown | Architect | C74826 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022