AdditionFull plan reviewIssued
Street view · Mar 2022
Google Street View of 1879 45th Av, Mar 2022
Scope of work
As written on the permit application.

Floor 1- partially demo (e) concrete slab and lower to achieve 7'-6" clear head height. construct rear yard addition to accomodate (n) kitchen and dining room. construct (n) interior staircase to floor 2. remodel interior to accomodate (n) bathroom, family room, mechanical room, and storage. floor 2

Timeline
Key dates from the city record.
Filed
May 28, 2026
Issued
Oct 5, 2026 (4 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
26 stops across 6 departments
Comments issued
6 times, by Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Apr 22, 2026Administrative

Zoning review

Planning · CP-ZOC

Apr 22, 2026Approved

Building plan review

Building Inspection · BLDG

Apr 23, 2026Denied

Permit Center

Permit Center · PERMIT-CTR

May 19, 2026Approved

Central Permit Bureau

Building Inspection · CPB

May 28, 2026Administrative

Zoning review

Planning · CP-ZOC

Jun 11, 2026Approved

Building plan review

Building Inspection · BLDG

Jul 23, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jul 23, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jun 27, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Jun 5, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jun 1, 2026Issued Comments

Urban forestry

Public Works · DPW-BUF

Jul 8, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jun 8, 2026Approved

Permit Processing Center

Building Inspection · PPC

Sep 10, 2026Administrative

Street use and mapping

Public Works · DPW-BSM

Jul 7, 2026Approved

Urban forestry

Public Works · DPW-BUF

Jul 8, 2026Approved

Zoning review

Planning · CP-ZOC

Aug 4, 2026Approved

Fire prevention review

Fire Department · SFFD

Aug 5, 2026Approved-Stipulated

Fire prevention review

Fire Department · SFFD

Aug 6, 2026Approved

Building plan review

Building Inspection · BLDG

Aug 10, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Aug 10, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 11, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 24, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Sep 2, 2026Approved

Urban forestry

Public Works · DPW-BUF

Sep 9, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Oct 5, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$217,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
David Townsend BrownArchitectC74826
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202604229866 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record