21 05th Av
San Francisco permit 202604229887 · Inner Richmond
Horizontal addition and renovation of (e) residence. excavate 1/f and replace foundations as required.
- Filed
- May 12, 2026
- Issued
- Sep 3, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 22 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 21, 2026 | May 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 13, 2026 | May 13, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 13, 2026 | Jun 26, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 13, 2026 | Jul 12, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 13, 2026 | Jul 12, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 13, 2026 | Jun 12, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 13, 2026 | May 14, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 13, 2026 | Jul 21, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | May 13, 2026 | Jun 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 13, 2026 | May 29, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | May 13, 2026 | Aug 28, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Jul 20, 2026 | Jul 21, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 29, 2026 | Jul 30, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 30, 2026 | Jul 30, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 31, 2026 | Jul 31, 2026 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Aug 4, 2026 | Aug 4, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 4, 2026 | Aug 4, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 6, 2026 | Aug 13, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 6, 2026 | Aug 27, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 6, 2026 | Aug 7, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Aug 27, 2026 | Aug 28, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 28, 2026 | Sep 3, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,200,000
| Name | Role | License on permit |
|---|---|---|
| Emily R Huang Huang Iboshi Architecture | Architect | C26901 |
| David Kallmeyer Gfds Engineers | Engineer | C-54247 |
| Benjamin Pan-Hon Lai Benjamin P.Lai & Associates | Engineer | 3268 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2015