2828 Vallejo St
San Francisco permit 202604290292 · Pacific Heights
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Rev to 202406063863.reconfig intf framing.replace extr wdws and doors;roof tiles and wood siding.upgrade mep.r/r elevator shaft/equipment and extend basement level; remove 2-story addition located on w/s bldg.build new 2-story addition in place 992sf).r/r (e) brick retaining wall on e/s of drwy.
- Filed
- Jun 1, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 17 stops across 6 departments
- Comments issued
- 5 times, by Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 24, 2026 | May 4, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 15, 2026 | May 28, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 1, 2026 | Jun 1, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 1, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Jun 1, 2026 | Jul 21, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 1, 2026 | Jul 21, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 1, 2026 | Jul 23, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 1, 2026 | Jun 9, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 1, 2026 | Jun 3, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 1, 2026 | Jul 13, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 1, 2026 | Jun 10, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 1, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $400,000
| Name | Role | License on permit |
|---|---|---|
| Suzette Anne Smith | Architect | C-30980 |
| Jillian Van Enckevort Ftf | Engineer | S5394 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2015