259 Maynard St
San Francisco permit 202604300437 · Excelsior
Add an interior stair connecting the (e) level 1 with the (e) basement. convert the storage area in the basement into habitable space. replace the (e) furnace & water heater & remove the (e) exteior wd stair at the rear yard.
- Filed
- Jun 3, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 16 stops across 6 departments
- Comments issued
- 4 times, by Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 27, 2026 | May 18, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 19, 2026 | Jun 1, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 2, 2026 | Jun 4, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 4, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Jun 4, 2026 | Jul 30, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 4, 2026 | Jul 29, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Jun 4, 2026 | Jun 27, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 4, 2026 | Jun 5, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jun 4, 2026 | Jun 10, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 4, 2026 | Jul 28, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 4, 2026 | Jun 29, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 4, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $181,000
| Name | Role | License on permit |
|---|---|---|
| Mark Kevin Hogan Openscope Studio | Architect | C33268 |
| Shaun Edward Moynahan Semco Engineering | Engineer | S4605 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025