8027 Geary Bl
San Francisco permit 202605010459 · Outer Richmond
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision pa#: 202505015573, reconfigure (e) ground floor unit - reconfigure (e) upper unit entry hall + stairs - infill portion of (e) lightwell at 2nd flr - remove (e) 2 -story deck + stair at rear. add (n) cantilverered decks at 2nd + 3rd flr - reconfigure to all exterior elevations.
- Filed
- Jun 23, 2026
- Issued
- Sep 28, 2026 (3 months after filing)
- Completed
- Not completed yet
- Review stops
- 26 stops across 5 departments
- Comments issued
- 6 times, by Permit Center, Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 1, 2026 | May 1, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 1, 2026 | May 1, 2026 | Approved |
Permit Center Permit Center · PERMIT-CTR | May 6, 2026 | May 18, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 20, 2026 | Jun 1, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 2, 2026 | Jun 23, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 23, 2026 | Jun 30, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 23, 2026 | Aug 28, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 23, 2026 | Aug 21, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 23, 2026 | Jul 16, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 23, 2026 | Jul 2, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 23, 2026 | Jun 25, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 23, 2026 | Sep 18, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jul 6, 2026 | Jul 7, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 6, 2026 | Jul 8, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 6, 2026 | Jul 8, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 6, 2026 | Aug 19, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 6, 2026 | Aug 17, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 6, 2026 | Aug 14, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 6, 2026 | Aug 11, 2026 | Approved |
Zoning review Planning · CP-ZOC | Sep 8, 2026 | Sep 9, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 8, 2026 | Sep 17, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 8, 2026 | Sep 16, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2026 | Sep 16, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 8, 2026 | Sep 9, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 8, 2026 | Sep 10, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 18, 2026 | Sep 28, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $8,000
| Name | Role | License on permit |
|---|---|---|
| Robert W Bradsby Robert Bradsby Architect | Architect | C19001 |
| Victor Ramos Ashley & Vance Engineering | Engineer | C86568 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019