546 Ellsworth St
San Francisco permit 202605010553 · Bernal Heights
1/f: remodel garage & to include addition of full bath and 2 bedrooms. 2/f: remodel (e) bathrooms & kitchen and replace front stairs. 3/f: add primary bedroom, closet & bathroom. foundation under seperate permit # 202604239965.
- Filed
- Jul 9, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 21 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 1, 2026 | May 1, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 8, 2026 | May 8, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 4, 2026 | Jun 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 8, 2026 | Jun 8, 2026 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jun 15, 2026 | Jul 7, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 8, 2026 | Jul 9, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jul 9, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Jul 9, 2026 | Sep 18, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 9, 2026 | Sep 17, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Jul 9, 2026 | Jul 28, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 9, 2026 | Jul 13, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 9, 2026 | Jul 16, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 9, 2026 | Jul 28, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 9, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Oct 28, 2026 | In progress | In Progress |
Mechanical and energy plan review Building Inspection · MECH | Oct 28, 2026 | Nov 3, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Oct 28, 2026 | Oct 29, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 28, 2026 | Oct 28, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 28, 2026 | Oct 30, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $120,000
| Name | Role | License on permit |
|---|---|---|
| Mark Jeffrey Topetcher Topetcher Architectural | Architect | C21678 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025