1558 15th St
San Francisco permit 202605050695 · Mission
Change of use approved under 202512161870. t.i. improvements include soft demo, mezzanine structure, partitions, accessible features, and restrooms, elect and lights. mechanial deferred.
- Filed
- May 5, 2026
- Issued
- May 28, 2026 (within 1 month of filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2026 were typically issued within 1 month (median of 3,682 issued permits).
- Review stops
- 15 stops across 4 departments
- Comments issued
- 3 times, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 5, 2026 | May 5, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 5, 2026 | May 5, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | May 7, 2026 | May 7, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 7, 2026 | May 7, 2026 | Approved-Stipulated |
Electrical plan review Building Inspection · MECH-E | May 7, 2026 | May 7, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 7, 2026 | May 7, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | May 7, 2026 | May 7, 2026 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | May 7, 2026 | May 7, 2026 | Approved |
Intake Building Inspection · INTAKE | May 8, 2026 | May 8, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | May 12, 2026 | May 12, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | May 20, 2026 | May 20, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 21, 2026 | May 21, 2026 | Approved |
Zoning review Planning · CP-ZOC | May 27, 2026 | May 27, 2026 | Approved |
Development fee collection Building Inspection · DFCU | May 27, 2026 | May 27, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 28, 2026 | May 28, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $717,500
| Name | Role | License on permit |
|---|---|---|
| Elmer W Lin Consortium | Architect | C31776 |
| Kam Wing Yan | Engineer | S3312 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025