65 Loraine Ct
San Francisco permit 202605050719 · Lone Mountain/USF
Interior remodel w/ added roof deck set back 17'-10"from(e)facade.remodel includes a 2'-11" expansion on the 1st fl not extending beyond(e)floor above(n) elec,plum, structural,skylights,& interior finishes.maximum excavation 1'-6",total soil disturbance 12.8 cubic yards for foundation reinforcement.
- Filed
- Jun 7, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 22 stops across 5 departments
- Comments issued
- 7 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 30, 2026 | May 18, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 19, 2026 | Jun 1, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 2, 2026 | Jun 8, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 8, 2026 | Jun 30, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 8, 2026 | Jul 31, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 8, 2026 | Jul 27, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Jun 8, 2026 | Jul 5, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 8, 2026 | Jun 16, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 8, 2026 | Jul 1, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 8, 2026 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 18, 2026 | Sep 24, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 20, 2026 | Sep 20, 2026 | Approved-Stipulated |
Mechanical and energy plan review Building Inspection · MECH | Sep 25, 2026 | Sep 25, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 1, 2026 | Oct 2, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 14, 2026 | Oct 20, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 28, 2026 | Oct 28, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 28, 2026 | Oct 28, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 29, 2026 | Oct 30, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 30, 2026 | Oct 30, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Oct 30, 2026 | Oct 30, 2026 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Nov 2, 2026 | In progress | In Progress |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Joshua Gary Larson Larson Shores Arch. | Architect | C30627 |
| Paul Chan Pctc Engineering | Engineer | C59840 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024