1681 10th Av
San Francisco permit 202605141234 · Inner Sunset
Unlawful demolition of a 2-story, type-v, single family residential dwelling. to comply with nov#202064291
- Filed
- Aug 21, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 14 stops across 6 departments
- Comments issued
- Twice, by Permit Center, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 8, 2026 | May 27, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jul 9, 2026 | Jul 28, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 21, 2026 | Aug 21, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 21, 2026 | Aug 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 21, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Aug 21, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 21, 2026 | Sep 16, 2026 | Not Applicable |
Fire prevention review Fire Department · SFFD | Aug 21, 2026 | Aug 25, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 21, 2026 | Aug 27, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 21, 2026 | Sep 8, 2026 | Not Applicable |
Public Utilities programs review Public Utilities · SFPUC-PRG | Aug 21, 2026 | Sep 18, 2026 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Aug 21, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Demolitions
- Status
- Filed
- Estimated cost
- $40,000
| Name | Role | License on permit |
|---|---|---|
| David George Yama Yama Architecture | Architect | C32627 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2019