CheckMyDesigner

329 Eureka St

San Francisco permit 202605151374 · Castro/Upper Market

AdditionFull plan reviewIssued
Street view · May 2025
Google Street View of 329 Eureka St, May 2025
Scope of work
As written on the permit application.

Interior remodel and rear horizontal extension. new deck over rear extension.

Timeline
Key dates from the city record.
Filed
Jun 1, 2026
Issued
Oct 7, 2026 (4 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
28 stops across 6 departments
Comments issued
3 times, by Fire Department, Public Works, Public Utilities
Review stopFinishedResult

Intake

Building Inspection · INTAKE

May 15, 2026Administrative

Zoning review

Planning · CP-ZOC

May 15, 2026Approved

Building plan review

Building Inspection · BLDG

May 15, 2026Administrative

Permit Center

Permit Center · PERMIT-CTR

May 29, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jun 1, 2026Administrative

Zoning review

Planning · CP-ZOC

Jun 9, 2026Approved

Building plan review

Building Inspection · BLDG

Aug 28, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Jul 23, 2026Not Applicable

Mechanical and energy plan review

Building Inspection · MECH

Sep 1, 2026Approved

Fire prevention review

Fire Department · SFFD

Jun 5, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jun 10, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jun 16, 2026Issued Comments

Permit Processing Center

Building Inspection · PPC

Sep 15, 2026Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Jul 6, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Jul 13, 2026Approved

Zoning review

Planning · CP-ZOC

Aug 20, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Aug 26, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 25, 2026Approved

Fire prevention review

Fire Department · SFFD

Sep 2, 2026Approved-Stipulated

Fire prevention review

Fire Department · SFFD

Sep 4, 2026Approved

Zoning review

Planning · CP-ZOC

Sep 15, 2026Approved

Building plan review

Building Inspection · BLDG

Sep 8, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 10, 2026Approved

Fire prevention review

Fire Department · SFFD

Sep 8, 2026Approved-Stipulated

Fire prevention review

Fire Department · SFFD

Sep 9, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Sep 10, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 15, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Oct 7, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$389,494
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Rex Stuart Mclean

Rex Mclean Architects

ArchitectC-14477
Kathryn Briggs

Base Design

Engineer5732
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202605151374 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record