371 Banks St
San Francisco permit 202605191496 · Bernal Heights
1/f: remodel - addition of bonus room on 1/f. new windows and doors at street and back. new stairs up to entry
- Filed
- Jun 8, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 30 stops across 5 departments
- Comments issued
- 7 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 18, 2026 | Jun 3, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 8, 2026 | Jun 8, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 8, 2026 | Jun 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 8, 2026 | Aug 1, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 8, 2026 | Aug 1, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 8, 2026 | Jul 5, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 8, 2026 | Jun 15, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 8, 2026 | Jul 6, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 8, 2026 | Oct 27, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 18, 2026 | Aug 18, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 18, 2026 | Aug 18, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 18, 2026 | Aug 25, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 18, 2026 | Aug 20, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 18, 2026 | Aug 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 27, 2026 | Sep 1, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 27, 2026 | Sep 1, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Sep 15, 2026 | Sep 15, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 18, 2026 | Sep 18, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 29, 2026 | Sep 29, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 29, 2026 | Sep 29, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 29, 2026 | Oct 5, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 29, 2026 | Oct 21, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 29, 2026 | Sep 30, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 5, 2026 | Oct 5, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Oct 21, 2026 | Oct 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 21, 2026 | Oct 22, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 21, 2026 | Oct 26, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Oct 21, 2026 | Oct 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 21, 2026 | Oct 23, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 27, 2026 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $450,000
| Name | Role | License on permit |
|---|---|---|
| Grace Harter O'rourke 444 Architects | Architect | C37272 |
| Marcus Yan Sf Bay Engineering | Engineer | C83553 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025