2154 44th Av
San Francisco permit 202605191499 · Sunset/Parkside
Vertical addition, remodel existing 1/f, reconfigure kitchen, bath and dining room. add stairway to new 2/f, add new 2/f with 3 bedrooms, 3 bathrooms and laundry.
- Filed
- Jun 2, 2026
- Issued
- Sep 23, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 26 stops across 6 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 15, 2026 | Jun 1, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 1, 2026 | Jun 2, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 2, 2026 | Jun 3, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 2, 2026 | Jul 25, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 2, 2026 | Jul 25, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Jun 2, 2026 | Jul 1, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 2, 2026 | Jun 3, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 2, 2026 | Jun 4, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jun 2, 2026 | Aug 5, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 2, 2026 | Jun 24, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 2, 2026 | Sep 17, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Jul 10, 2026 | Jul 13, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 11, 2026 | Aug 19, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 11, 2026 | Aug 11, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 12, 2026 | Aug 12, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 12, 2026 | Aug 12, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 17, 2026 | Aug 17, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 26, 2026 | Aug 26, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 27, 2026 | Aug 27, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 28, 2026 | Aug 31, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 28, 2026 | Sep 3, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Aug 28, 2026 | Aug 31, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 28, 2026 | Sep 11, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 28, 2026 | Sep 3, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 16, 2026 | Sep 16, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 17, 2026 | Sep 23, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $513,819
| Name | Role | License on permit |
|---|---|---|
| James Treman Jim Treman Architect | Architect | C32958 |
| Ca Hien Voong Ca Voong | Engineer | 56997 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2014