Revision to pa# 202101192880, to use state adu program instead of local program, to remove the fire sprinklers as no longer required under adu r3, keep 2ft existing nonconforming rear structure, remove side door into exterior hallway. no change to building envelope.
- Filed
- Jun 4, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 29 stops across 5 departments
- Comments issued
- 11 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 18, 2026 | Jun 4, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 4, 2026 | Jun 5, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 5, 2026 | Jun 17, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 5, 2026 | Jul 2, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 5, 2026 | Jul 2, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 5, 2026 | Jul 1, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 5, 2026 | Jun 15, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 5, 2026 | Jun 9, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 5, 2026 | Jul 15, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 5, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Jul 20, 2026 | Aug 3, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 31, 2026 | Aug 17, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 17, 2026 | Aug 17, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 17, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 17, 2026 | Aug 25, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 17, 2026 | Aug 25, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 17, 2026 | Aug 20, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 17, 2026 | Aug 25, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 10, 2026 | Sep 10, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 28, 2026 | Sep 29, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 28, 2026 | Oct 5, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 28, 2026 | Oct 5, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 28, 2026 | Oct 20, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 28, 2026 | Sep 30, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 28, 2026 | Oct 28, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 16, 2026 | In progress | In Progress |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $1,000
| Name | Role | License on permit |
|---|---|---|
| Luis Antonio Robles Robles & Associates Arch | Architect | C21700 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025