1082 Rhode Island St
San Francisco permit 202605201638 · Potrero Hill
1)widen garage door. 2)widden garage, 3)repostion front entry, 4)adjust e stair to lower floor, 5)infill lightwell, 6)conversion of storage area to conditioned space, 7)infill balcony at 2nd floor, 8)add deck and stair at rear yard,
- Filed
- Sep 17, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 21 stops across 6 departments
- Comments issued
- 6 times, by Planning, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 20, 2026 | May 20, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 21, 2026 | May 21, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 2, 2026 | Jun 2, 2026 | Issued Comments |
Intake Building Inspection · INTAKE | Aug 6, 2026 | Aug 6, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 19, 2026 | Aug 19, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 20, 2026 | Aug 20, 2026 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Aug 28, 2026 | Sep 16, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 1, 2026 | Sep 17, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 17, 2026 | Sep 17, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 17, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Sep 17, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 17, 2026 | Oct 16, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 17, 2026 | Sep 21, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 17, 2026 | Sep 30, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 17, 2026 | Oct 5, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 17, 2026 | In progress | — |
Zoning review Planning · CP-ZOC | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $450,000
| Name | Role | License on permit |
|---|---|---|
| Pezhman Motevaseli Rdk Consulting | Engineer | C78170 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022