1301 Noriega St
San Francisco permit 202605292210 · Sunset/Parkside
Ground floor retail bank branch ti no strurtural partitions, ceilings, finishes and mep.
- Filed
- May 29, 2026
- Issued
- Oct 1, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2026 were typically issued within 1 month (median of 3,682 issued permits).
- Review stops
- 11 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 29, 2026 | May 29, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 1, 2026 | Jun 1, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | Jun 1, 2026 | Jun 1, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 1, 2026 | Jun 1, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 1, 2026 | Jun 1, 2026 | Not Applicable |
Electrical plan review Building Inspection · MECH-E | Jun 2, 2026 | Jun 2, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 18, 2026 | Jun 18, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 18, 2026 | Jun 18, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 22, 2026 | Jun 22, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 29, 2026 | Jun 29, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 1, 2026 | Oct 1, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $850,000
| Name | Role | License on permit |
|---|---|---|
| Michael Jansen Zelazek | Architect | C34048 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2021