231 Onondaga Av
San Francisco permit 202606042505 · Outer Mission
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa#201908088315 to modify approved layout at unit 231b-reduction of 2nd floor rear deck & remove of stairs. pa #201908088326,roof dormer window to replace in the e opening under pa #201908088326. legalize of the other unit under pa#201908088326
- Filed
- Jun 4, 2026
- Issued
- Aug 25, 2026 (3 months after filing)
- Completed
- Not completed yet
- Review stops
- 6 stops across 3 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 4, 2026 | Jun 4, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 4, 2026 | Jun 4, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | Jun 4, 2026 | Jun 4, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 4, 2026 | Jun 4, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 4, 2026 | Jun 4, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 25, 2026 | Aug 25, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $40,000
| Name | Role | License on permit |
|---|---|---|
| Pezhman Motevaseli Rkd Consulting Inc. | Architect | C78170 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025