3042 Pierce St #0
San Francisco permit 202606052627 · Marina
Front building:build new residential unit 3048 (not adu) in existing ground level storage room in the front building of 3042-3046 pierce street.work is within the buildings existing footprint.work will include new walls,new windows, new doors to build a new two unit one bathroom unit.
- Filed
- Jul 16, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 21 stops across 6 departments
- Comments issued
- 9 times, by Permit Center, Planning, Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 1, 2026 | Jun 18, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jun 23, 2026 | Jul 13, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 13, 2026 | Jul 17, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jul 17, 2026 | Aug 13, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 17, 2026 | Aug 21, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 17, 2026 | Aug 21, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 17, 2026 | Aug 7, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 17, 2026 | Jul 27, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 17, 2026 | Jul 22, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jul 17, 2026 | Aug 19, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 17, 2026 | Jul 29, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jul 17, 2026 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Aug 12, 2026 | Aug 13, 2026 | Approved |
Zoning review Planning · CP-ZOC | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $147,000
| Name | Role | License on permit |
|---|---|---|
| David Scott Locicero David Locicero | Engineer | C19452 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025